- Mar 6, 2024
Thank you again for your continued patience and cooperation through our renovation. We continue to make significant progress at the 643. Here’s a look at what we accomplished over the last two weeks and what’s ahead.
Â
The past two weeks
Substantial completion of demolition
Framing on floors 5-8. Layout on floors 3-5
-MEP overhead rough on floors 5, 6, 7, & 8
-MEP in-wall rough on floors 6, 7, & 8
-Steel fireproof patching to start on the 7th floor
Â
Next Week
First inwall inspection on floors 7 and 8
MEP overhead rough on floors 3-5
Framing will continue on floors 4 and 5
Parapet investigation on the 8th-floor terrace.
Â
General Reminders
Parking is not available in the garage or surface lot during construction.
Â
Remember to check the project website updatesatthe643.com for more information, including virtual tours, high performance and technology used on the 643 project. Have a great weekend!