Phase 2 Update 2/16/24

  • agertz
  • Feb 16, 2024
  • 1 min read

Things are moving quickly on the 643 Phase 2 project and we’re back to give you bi-weekly updates and photos of our progress.  

 

 This Week

· Demolition on the third and fourth floors.

· SPG Drywall is doing the layout on floors six, seven and eight. 

· First material delivery with a crane. (photo attached) 

· MEP Layout and coring have started.

 

 



Next Week 

· Demolition will be completed.

· SPG Drywall will continue layout on the fourth and 5th floors.

· Continued MEP layout and coring.

· Overall electrical and mechanical rough-ins.

 

General Reminders

· Parking is not available in the garage or surface lot during construction.

 

Thank you again for your continued patience and cooperation through our renovation. 

 

 

 
 
 