Phase 2 Update 3/1/24

  • agertz
  • Mar 6, 2024
  • 1 min read

Thank you again for your continued patience and cooperation through our renovation. We continue to make significant progress at the 643. Here’s a look at what we accomplished over the last two weeks and what’s ahead.

 

The past two weeks

  • Substantial completion of demolition

  • Framing on floors 5-8. Layout on floors 3-5

  • -MEP overhead rough on floors 5, 6, 7, & 8

  • -MEP in-wall rough on floors 6, 7, & 8

  • -Steel fireproof patching to start on the 7th floor

 

Next Week

  • First inwall inspection on floors 7 and 8

  • MEP overhead rough on floors 3-5

  • Framing will continue on floors 4 and 5

  • Parapet investigation on the 8th-floor terrace.

 

General Reminders

  • Parking is not available in the garage or surface lot during construction.

 

Remember to check the project website updatesatthe643.com for more information, including virtual tours, high performance and technology used on the 643 project. Have a great weekend!

 