Weekly Progress Update 1/6/23

  • agertz
  • Jan 9, 2023
  • 1 min read



This Week

  • Started putting the framing back together in exterior parking area ceiling

  • Installed ceramic tile in restrooms

  • Painted walls and ceiling on second floor

  • Ceiling close-up inspection on the second floor

  • Drywall and taping of ceilings after inspection

  • Drop ceiling tile


Next Week

  • Continuing thermal insulation around exterior beam enclosures on first floor

  • Mechanical rough-in on first floor ceiling

  • Drywalling walls on the first floor

  • Start floor prep on second floor

  • Start ceiling work above monumental staircase

  • Continuing ceramic tiles in the restrooms

  • Shade infrastructure installation

  • Starting the curtain wall


Below are some activities taking place next week as we continue to stay on schedule.

General reminders

  • During construction, parking spaces have been assigned. Please ensure that you use only your spot or park offsite.

  • Visitors will not be able to park in the lot and visiting employees should be prepared to find remote parking. Double parking will not be permitted.

  • Emergency issues related to the 643 renovations should be routed to Jack Brown at 847-338-4308.

  • All general building maintenance/engineering issues should still be sent to Tom Brannon at 847-609-7893.