Weekly Progress Update 2/3/23
- agertz
- Feb 3, 2023
- 1 min read
The main lobby will undergo demolition and construction work this weekend. The office will be closed 2/4-5.
This Week
Carpet installation started on second floor
Started taping first floor ceiling
Painted first floor ceiling
Started glass curtainwall
This Weekend
Install terrazzo in the lobby
Next Week
Stair scaffolding will be removed
Millwork delivery
Door delivery
Continue installing carpet
Finish glass curtainwall install on the first floor
Start installing roof curbs for mechanical equipment
Deliver and install operable partition
Below are some activities taking place next week as we continue to stay on schedule.
General reminders
During construction, parking spaces have been assigned. Please ensure that you use only your spot or park offsite.
Visitors will not be able to park in the lot and visiting employees should be prepared to find remote parking. Double parking will not be permitted.
Emergency issues related to the 643 renovations should be routed to Jack Brown at 847-338-4308.
All general building maintenance/engineering issues should still be sent to Tom Brannon at 847-609-7893.
Commentaires