Weekly Progress Update 2/3/23

  • agertz
  • Feb 3, 2023
  • 1 min read



The main lobby will undergo demolition and construction work this weekend. The office will be closed 2/4-5.


This Week

  • Carpet installation started on second floor

  • Started taping first floor ceiling

  • Painted first floor ceiling

  • Started glass curtainwall

This Weekend

  • Install terrazzo in the lobby


Next Week

  • Stair scaffolding will be removed

  • Millwork delivery

  • Door delivery

  • Continue installing carpet

  • Finish glass curtainwall install on the first floor

  • Start installing roof curbs for mechanical equipment

  • Deliver and install operable partition


Below are some activities taking place next week as we continue to stay on schedule.

General reminders

  • During construction, parking spaces have been assigned. Please ensure that you use only your spot or park offsite.

  • Visitors will not be able to park in the lot and visiting employees should be prepared to find remote parking. Double parking will not be permitted.

  • Emergency issues related to the 643 renovations should be routed to Jack Brown at 847-338-4308.

  • All general building maintenance/engineering issues should still be sent to Tom Brannon at 847-609-7893.