Weekly Progress Updates 1/20/23

  • agertz
  • Jan 26, 2023
  • 1 min read

The main lobby will undergo demolition and construction work for three consecutive weekends. The office will be closed 1/21-22, 1/28-29 and 2/4-5.


This Week

  • Started to paint walls on the first floor and ceilings on the second floor

  • Started terrazzo tile on the second floor

  • Started floor prep on the second floor

  • Installed bathroom countertops and plumbing fixtures

  • Framed the first floor phase one ceiling

  • Sprayed acoustic ceiling treatment

  • Started second floor glass handrail

This Weekend

  • Demolition of the flooring at the first floor elevator lobby

  • Demolition and framing of the ceiling at the first floor elevator lobby


Next Week

  • Starting the curtain wall

  • Ceiling inspection

  • Installing terrazzo on the second floor

  • Begin floor prep in the wood and carpet areas

  • Install ceiling grid on the first floor

  • Install exterior drywall ceilings


Below are some activities taking place next week as we continue to stay on schedule.

General reminders

  • During construction, parking spaces have been assigned. Please ensure that you use only your spot or park offsite.

  • Visitors will not be able to park in the lot and visiting employees should be prepared to find remote parking. Double parking will not be permitted.

  • Emergency issues related to the 643 renovations should be routed to Jack Brown at 847-338-4308.

  • All general building maintenance/engineering issues should still be sent to Tom Brannon at 847-609-7893.